The construction of a new overbridge on the Coventry Road, that will allow high-speed trains to travel across four tracks under the A45, has reached the pivotal halfway mark.
Over the past eleven months, a team of engineers working for HS2’s construction partner Balfour Beatty VINCI (BBV), have successfully completed the first section of the new Coventry Road overbridge, near Bickenhill. This unique structure is being constructed in two halves, to ensure that existing traffic flows along the A45 are maintained, minimising impacts on the local road network.
Using the ‘top down’ construction method, approximately 7,5000 tonnes of earth was excavated from beneath the existing carriageway. The team then installed 46 piles, at depths of up to 23 metres, and built the pile caps to support the weight of the new 2,000-tonne bridge deck.
Over the summer months, 13 pre-stressed pre-cast concrete beams were lowered into place to support the 37-metre span bridge deck, and 13 parapet units were successfully installed to one half of the structure.
Completion of the waterproofing and highway works in the coming weeks means the eastbound section of the new structure will soon be brought into use, and HS2 is working closely with National Highways to prepare for the upcoming traffic management changes.
From Monday 7 December, a series of overnight and weekend closures will be put in place to facilitate the traffic switchover. Once complete, motorists will begin using the temporary carriageway alignment over the new eastbound section of the bridge.
Paul Marshall, Head of Delivery at HS2 Ltd said:
“Our engineers have worked incredibly hard to develop a design solution that maintains traffic flows in each direction, while we build the bridge and excavate the ground below to make way for the new high-speed railway.
“During the temporary weekend and night-time closures, to facilitate the traffic switchover onto the new bridge, we’ll ensure that access to businesses and properties is maintained.
In the new year, BBV’s engineering team will start work on the second section of the bridge, following a similar sequence of works.