The completion date for a £36 million scheme to create a new junction on the A34 in Oxfordshire has been pushed back to next year, the county council has said
Work began on the A34 Lodge Hill Junction in Abingdon in October 2025, with an initial date for its completion – following a series of set backs caused by other roadworks and housing developments – given as ‘winter 2026’, reports the Oxford Mail.
That date has now been pushed back to spring 2027 due to roadworks on the Peachcroft roundabout by housing developer David Wilson continuing through December up to Christmas.
Some aspects of the A34 Lodge Hill were temporarily paused in October ‘to improve traffic flow and safety’ during the Peachcroft roadworks, the council said.
With three stages of the works completed, stage four is underway and stage five is about to start, which involves realigning the northbound and building the southbound A34 slip roads, building sections of the north and south roundabouts and creating an access road.
Councillor Liz Leffman, Oxfordshire County Council’s cabinet member for highways construction and repair, said:
“On a project of this scale, maintaining a safe and workable traffic management arrangement while construction continues on this very busy part of the network is critical.
“Unfortunately, the overlap in traffic management requirements for the two schemes means that we will not now be able to achieve the previously hoped-for completion before Christmas. The scheme continues to make good progress, and we are now working towards completion in early spring 2027.
“Our contractors and the project team remain firmly focused on maintaining momentum over the coming months and bringing the new junction infrastructure into use as soon as it is safe and practical to do so.”
(Picture: Oxfordshire County Council)