Galliford Try wins £210m contract to deliver M5 Junction 10 improvements

LinkedIn
X
Facebook
Email
Print

Galliford Try has secured a £210m contract from Gloucestershire County Council to deliver the main construction works for the M5 Junction 10 Improvements Scheme, which will create a full all-movements interchange and improve road connections around Cheltenham.

The contract forms part of a wider £372m infrastructure scheme designed to increase motorway capacity, improve connectivity and support planned housing and economic development to the west and north of Cheltenham.

The upgraded junction will allow motorists to join and leave the M5 in all directions for the first time, replacing the existing restricted-access arrangement.

The works will include the demolition of the existing A4019 motorway bridge and construction of two new bridges carrying a roundabout over the M5, supported by four new slip roads.

The project also includes a new 1.4km West Cheltenham Link Road, connecting the A4019 with the B4634, and widening of the A4019 Tewkesbury Road between Withybridge Lane and Gallagher Retail Park.

Additional improvements will provide new walking and cycling facilities, public transport enhancements and measures to manage flood risk.

Galliford Try has been involved in developing the scheme since 2023, working with the county council under an early contractor involvement arrangement. The latest contract award moves the project into its main construction phase.

Preparatory work has already included archaeological investigations, utility diversions, ecological mitigation and the establishment of site compounds.

Main construction is scheduled to begin in early 2027, with the principal elements of the scheme being delivered concurrently.

The existing northbound entry and southbound exit slip roads at Junction 10 are expected to close for approximately two years to allow the most complex construction activities to take place safely. The M5 itself will remain open, with signed diversion routes provided.

Physical construction is expected to be completed in spring 2029, followed by final snagging and handover through to spring 2031.

The improvements are expected to support the delivery of more than 20,000 new homes, including over 7,000 affordable properties, and help unlock major developments including the £1bn Golden Valley project and the National Cyber Innovation Centre close to GCHQ.

The wider development programme is also expected to support around 12,000 skilled jobs.

Funding for the overall scheme has been secured from a range of sources, including the Government’s Housing Infrastructure Fund, administered by Homes England.

Bill Hocking, chief executive of Galliford Try, said:

“Our Infrastructure business remains a key part of our Sustainable Growth Strategy and the team has a strong track record in delivering schemes for the strategic road network.

“We look forward to continuing our collaboration with Gloucestershire County Council following the successful design phase, and delivering this much-needed improvement scheme that will help unlock economic growth in the region.”

(Picture: Mapillary)