£300m of major Belfast infrastructure projects remain stalled amid funding and delivery uncertainty

LinkedIn
X
Facebook
Email
Print

Three major transport infrastructure schemes in Belfast, with a combined estimated cost of up to £317.5 million, remain without a clear route to construction, according to a report from Northern Ireland’s Department for Infrastructure (DfI).

The projects – the York Street Interchange, an expansion of the Belfast Glider rapid transit network and a pedestrian and cycle bridge across the River Lagan – are facing continued delays, with funding shortfalls and uncertainty over their future delivery.

The position is outlined in a DfI report due to be considered by Belfast City Council, highlighting the challenges facing three significant schemes intended to improve connectivity, reduce congestion and support sustainable travel across the city. The largest road scheme, the proposed redevelopment of York Street Interchange, would address a major bottleneck where Belfast’s Westlink meets the M2 and M3 motorways.

The planned scheme, extending almost two miles, would introduce underpasses to separate traffic travelling towards the motorways from vehicles entering the city.

The project was estimated to cost between £125 million and £160m in 2015, although those figures are now under review.

A design contract was halted following legal action in 2017, which was resolved two years later. However, the scheme subsequently entered a prolonged period of reviews, consultancy and further development work before being placed on indefinite hold in 2023.

The proposed Glider expansion is also facing significant financial challenges.

Plans include a new north-south route and an extension of the existing service between Titanic Quarter and Belfast city centre to Queen’s University.

The proposed additions are estimated to require £124.5 million, but less than 40% of the funding has so far been allocated.

The original north-south route was intended to connect Glengormley, north of Belfast, with Carryduff to the south. However, budget pressures and concerns over congestion have resulted in the proposals being scaled back.

The anticipated start of services has already moved from 2030 to 2033. Consultants were appointed during 2026 to progress the design phase, but DfI officials say a considerable funding shortfall remains, with £48 million currently available.

The third scheme is a pedestrian and cycle bridge spanning approximately 470ft across the River Lagan.

The proposed crossing would link Ormeau Embankment with the redeveloped Gasworks area, providing an additional active travel connection close to Belfast city centre.

The bridge, previously estimated to cost between £23 million and £28 million, was among three infrastructure projects placed on hold by Infrastructure Minister Liz Kimmins while she pursued an appeal against a court ruling blocking the A5 Western Transport Corridor project. Although the minister won that appeal last month, the bridge project has yet to receive the go-ahead to proceed.

The combined estimated cost of the three Belfast schemes is between £267.5 million and £317.5 million, although the DfI report cautions that some of the figures are based on estimates more than a decade old and may no longer reflect current costs.

The continued uncertainty raises questions over the delivery timetable for infrastructure intended to improve Belfast’s road network, public transport provision and active travel connections.